11 . TI Calculator Graded Problem Set You are evaluating a proposed project for your company. The project is expected to generate the following end-of-year
11 . TI Calculator Graded Problem Set
You are evaluating a proposed project for your company. The project is expected to generate the following end-of-year cash flows:
-3,000 300 300 600 600 800 800 800 400
You have been told you should evaluate this project with an interest rate of 9%. What is the project's NPV?
$169.58
$235.97
$101.62
$119.39
$51.43
Your group leader has now told you that the risk of the project was understated before. As a result, she tells you to recalculate the projects NPV with an 11% interest rate. What is the new NPV?
-$71.99
-$147.53
-$115.38
-$190.92
-$22.97
When the project was first evaluated at 9%, you would have advised that the company _______ the project because it ______________ value for the company. But now with an 11% interest rate, you will advise the company to __________ the project because it _____________ value for the company.
Calculate the projects internal rate of return (IRR).
10.81%
9.79%
9.41%
9.99%
13.38%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started