Question
11) Your auditor has notified you that while conducting an audit of a Hide-Um Corp proposal for the same product you currently have on contract
11) Your auditor has notified you that while conducting an audit of a Hide-Um Corp
proposal for the same product you currently have on contract with them, the auditor found
information that the contractor may have intentionally submitted vendor quotes that were
significantly higher than his actual costs. You double check your file and verify that Hide-
Um did submit certified cost or pricing data which you used to negotiate the final contract
price. Choose the reason why this scenario would put the contractor in debt with the
Government.
Choose one of the following?
- Billing overpayment
- Retroactive price reduction
- Defective pricing
- Breach of contract obligation
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started