Question
1.[15 points] Project Evergreen is to produce 300 garden solar lights and is scheduled to take five weeks. Each unit is planned to cost $81.
1.[15 points] Project Evergreen is to produce 300 garden solar lights and is scheduled to take five weeks. Each unit is planned to cost $81. The project is severely cost constrained. Performance data for the project at the end of week three is presented below:
120 total units were planned to be produced
130 units have actually been produced
The financial manager reported that the business had actually spent $16,650 on the project by the end of week three.
Answer the following questions; show all work:
a.Quantify cost variance. Is the project ahead or behind budget?
b.Quantify schedule variance. Is the project ahead or behind schedule?
c.Quantify cost performance efficiency. Is the project performing better or worse than planned?
d.Quantify schedule performance efficiency. Is the project performing better or worse than planned?
e.What is the forecast of project cost at completion assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?
f.What is the forecast of funding needed to complete the project (from this point forward)?
g.What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?
h.As the project financial manager, what recommendations would you make?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started