Question
11.Assume that a company has two cost driversnumber of courses and number of students. The planned number of courses and students were 5 and 100,
11.Assume that a company has two cost driversnumber of courses and number of students. The planned number of courses and students were 5 and 100, respectively. The actual number of courses and students were 6 and 110, respectively. One of the company's expenses is influenced by both cost drivers and it has a fixed element as well. Its cost formulas are $50 per course, $6 per student, and $1,000 per period. The total cost included in the planning budget for this expense would be:
rev: 06_25_2020_QC_CS-208650
Multiple Choice
- $1,850.
- $1,750.
- $1,960.
- $2,060.
13.Assume that a company's revenue in its flexible budget is $76,000. Its actual amount of revenue is $69,000 and the amount of revenue in the company's planning budget is $78,000. The amount of the revenue variance is:
rev: 06_25_2020_QC_CS-208650
Multiple Choice
- $7,000 F.
- $7,000 U.
- $5,000 U.
- $9,000 U.
16.Assume that a company has two cost driversnumber of courses and number of students. The planned number of courses and students were 5 and 100, respectively. The actual number of courses and students were 6 and 110, respectively. One of the company's expenses is influenced by both cost drivers. Its cost formulas are $50 per course and $4 per student. The total cost included in the flexible budget for this expense would be:
rev: 06_25_2020_QC_CS-208650
Multiple Choice
- $840.
- $540.
- $740.
- $640.
17.Assume the following information for one of a company's variable expenses:
- The activity variance is $760 favorable.
- The actual amount of the expense is $8,300.
- The planned level of activity is 1,000 hours.
- The actual level of activity is 900 hours.
The cost formula for this expense must be:
rev: 06_25_2020_QC_CS-208650
Multiple Choice
- $6.90 per hour.
- $7.90 per hour.
- $7.60 per hour.
- $8.60 per hour.
19.Assume that the amount of one of a company's variable expenses in its flexible budget is $40,000. The actual amount of the expense is $42,000 and the amount in the company's planning budget is $42,000. The activity variance for this expense is:
rev: 06_25_2020_QC_CS-208650
Multiple Choice
- $1,000 F.
- $1,000 U.
- $2,000 U.
- $2,000 F.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started