Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance

1.2 REQUIRED: Use the information provided below to calculate the following:

1.2.1 Idle time variance (3)

1.2.2 Labour mix variance (7)

1.2.3 Labour yield variance (3)

Indicate whether each variance is favourable or unfavourable.

INFORMATION:

Standard labour costs for Electro Manufacturers to manufacture 2 000 units:

400 hours at R70 per hour

200 hours at R35 per hour

Actual labour costs incurred to produce 1 900 units:

290 hours at R R65 per hour

170 hours at R32 per hour

Idle time represents 10% of the recorded labour hours

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing Theory A Systems View

Authors: Hugh Marsh, G A Swanson

1st Edition

089930608X, 978-0899306087

More Books

Students also viewed these Accounting questions