12-1) The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E

12-1)

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.

Item End B C D E F G H
LT (wk) 1 2 3 3 1 2 1 2
Amount on hand 0 10 10 25 12 30 5 0

a.

If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)

Additional units

b.

An order for the end item is scheduled to be shipped at the start of week 14. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)

The latest week

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting with International Financial Reporting Standards

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

4th edition

1119504309, 1-119-50340-8, 9781119503408 , 978-1119504306

More Books

Students also viewed these Accounting questions

Question

2. Information that comes most readily to mind (availability).

Answered: 1 week ago