13. Every project cost estimate must include documentation. Which of the following is NOT required to be included in the cost estimate documentation? o Accuracy
13. Every project cost estimate must include documentation. Which of the following is NOT required to be included in the cost estimate documentation? o Accuracy range of the estimate o Assumptions and constraints influencing the estimate o Rationale behind the project's identified business need o Values and calculations that were used