13 out of question Based on the activity network pictured, what is the BEST statement? 3 A 5 C D B O a. The
13 out of question Based on the activity network pictured, what is the BEST statement? 3 A 5 C D B O a. The critical path is ACD =.12 days O b. The critical path is ABCD = 16 days c. The critical path is ACD = 13 days d. The critical path is BCD = 13 days