14 of 14. While completing the Analyze the Schedule step of the project scheduling process you identified four possible project paths. You then added together
14 of 14. While completing the Analyze the Schedule step of the project scheduling process you identified four possible project paths. You then added together the duration of all the tasks on each path. The total duration for each path is listed below. Which one of these represents the critical path for this project? O Path 1 = 15 days O Path 2 = 18 days O Path 3 = 22 days O Path 4 = 26 days