Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

(14 points total) 3. Information is shown below for the last 5 activities in a project with many activities. The network corresponding to this is

(14 points total)

3. Information is shown below for the last 5 activities in a project with many activities. The network corresponding to this is shown below and in the table (M, N, O and P are activities before Q and R). The table also shows the earliest start (ES) times for activities Q and R.

Activity

Length

Predecessor

ES

EF

LS

LF

Slack

Q

6

N,O

49

R

5

M,P

57

S

4

Q

U

9

R

V

8

S,R

Q49 arrow to S arrow to V

R57 arrow to V

R57 arrow to U

(8 pts.) a) Fill in the table above with the earliest start (ES) and earliest finish (EF) times, the latest start (LS) and latest finish (LF) times and the slack for activities Q, R, S, U and V. (You can also fill in the boxes in the network with ES, EF, LS LF if you wish.)

(2 pt.) b) What is the minimum (earliest) completion time of the project?

(2 pt.) c) Which activities are on the critical path?

(2 pt.) d) Which activity (or activities) have the greatest slack and how large is that slack?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books

Students also viewed these General Management questions