15. Refer to Exercise 4 in Chapter 4. Ten days after the start of the project, the following information is received: Draw the updated network.
15. Refer to Exercise 4 in Chapter 4. Ten days after the start of the project, the following information is received:
Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any.
\begin{tabular}{ll} \hline Activities A and B & Completed on time \\ Activity C & Started; 3 days left \\ Activity D & Started; 2 days left \\ Activity E & Has not started yet but duration adjusted to 5 days \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started