Question

1 Approved Answer

15. Refer to Exercise 4 in Chapter 4. Ten days after the start of the project, the following information is received: Draw the updated network.

15. Refer to Exercise 4 in Chapter 4. Ten days after the start of the project, the following information is received:

image text in transcribed

Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any.

\begin{tabular}{ll} \hline Activities A and B & Completed on time \\ Activity C & Started; 3 days left \\ Activity D & Started; 2 days left \\ Activity E & Has not started yet but duration adjusted to 5 days \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Analytics Methods Models And Decisions

Authors: James R. Evans

2nd Edition

321997824, 978-1119298588, 978-0321997821

More Books

Students also viewed these General Management questions