Question

1 Approved Answer

15 years ago, a 200-MW thermal power plant cost $100 million. The cost index for this class of equipment 15 years ago was 400 and

15 years ago, a 200-MW thermal power plant cost $100 million. The cost index for this class of equipment 15 years ago was 400 and is now 1200. The cost capacity factor is 0.71. The plant engineering staff is considering a 600-MW unit of the same general design to power another section. Assume we want to add a pre-compressor, which currently costs $28,000. Determine the total cost of the 600-MW unit.

please it is urgent and I need to know the solution asap. Thanks in advance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Christian Case For Bitcoin

Authors: Dr Patrick C. Melder

1st Edition

979-8201772208

More Books

Students also viewed these Finance questions