17. Company W detemined that its standard number of hours that should have worked for the output attained is 2,000 direct labor bours and the
17. Company W detemined that its standard number of hours that should have worked for the output attained is 2,000 direct labor bours and the actual number of direct labor hours worked was 2,100 . The total labor price variance was $525 unfavorable, and the standard rate of pay was S15 per direct labor hour, what was the actual rate of pay for direct labor? A) $15.20 C) 515.25 B) $14,75 D) $15.00