17. The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task D assuming
17.
The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task D assuming an early start?
Task | Predecessor(s) | Duration (Days) | Cost per Day |
A | -- | 5 | $1,000 |
B | A | 6 | $2,000 |
C | A | 10 | $1,000 |
D | C | 8 | $3,000 |
E | B | 7 | $2,000 |
F | D, E | 6 | $1,000 |
a. | $6,000 | |
b. | $12,000 | |
c. | $9,000 | |
d. | $3,000 | |
e. | $0 |