17-If you have a cost variance of $500, this would indicate:a. Earned value is less than actual costb. Earned value is less than estimate at
17-If you have a cost variance of $500, this would indicate:a. Earned value is less than actual costb. Earned value is less than estimate at completionc. Actual cost is less than earned valued. The ra