Question
1 Approved Answer
18 - Use this information to answer the question that follow. The standard costs and actual costs for factory overhead for the manufacture of 2,600
18 - Use this information to answer the question that follow. The standard costs and actual costs for factory overhead for the manufacture of 2,600 units of actual production are as follows:
Standard Costs | |
Fixed overhead (based on 10,000 hours) | 3 hours per unit @ $0.77 per hour |
Variable overhead | 3 hours per unit @ $1.92 per hour |
Actual Costs | |
Total variable cost, $17,900 | |
Total fixed cost, $7,800 |
The variable factory overhead controllable variance is
a.$2,924 favorable
b.$0
c.$2,339 favorable
d.$2,924 unfavorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started