Question
1.A company has 4 departments as follow: ->E -> F->G-> H -> Processing speed in minutes/unit: E = 10; F = 12; G = 9;
1.A company has 4 departments as follow:
->E -> F->G-> H ->
Processing speed in minutes/unit: E = 10; F = 12; G = 9; H = 8.
a.Which department is the bottleneck department?
b.Calculate the flow time or the average time (in minutes) it takes for a unit to move through an entire process from department E to H.
c.What is the system output or throughput rate in units/hr? 1 week = 5 working days and 1 working day = 8 hours. What is the system output or throughput rate in units/week?
d.I would like to increase the system output, which department is the focus of my improvement effort? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started