1.A company has 4 departments as follow: ->E -> F->G-> H -> Processing speed in minutes/unit: E = 10; F = 12; G = 9;

1.A company has 4 departments as follow:

->E -> F->G-> H ->

Processing speed in minutes/unit: E = 10; F = 12; G = 9; H = 8.

a.Which department is the bottleneck department?

b.Calculate the flow time or the average time (in minutes) it takes for a unit to move through an entire process from department E to H.

c.What is the system output or throughput rate in units/hr? 1 week = 5 working days and 1 working day = 8 hours. What is the system output or throughput rate in units/week?

d.I would like to increase the system output, which department is the focus of my improvement effort? Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elementary Technical Mathematics

Authors: Dale Ewen

12th Edition

1337630586, 978-1337630580

More Books

Students also viewed these Mathematics questions