Question
1a. Compute the following variances for June, materials price and quantity variances. 1b. Compute the following variances for June, labor rate and efficiency variances. 1c.
1a. Compute the following variances for June, materials price and quantity variances.
1b. Compute the following variances for June, labor rate and efficiency variances.
1c. Compute the following variances for June, variable overhead rate and efficiency variances.
(Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
!a. Material Price Variance
Material quantity variance
1b. Labor rate variance
Labor efficiency variance
1c. Variance Overhead rate variance
Variable overhead efficiency variance
Net variance
Problem 9-18 Comprehensive Variance Analysis (LO9-4, LO9-5, LO9-6] Miller Toy Company manufactures a plastic swimming pool at its Westwood Plant. The plant has been experiencing problems as shown by its June contribution format income statement below: Flexible Budget Actual Sales (5,000 pools) $ 272,000 $272,000 Variable expenses: Variable cost of goods 84,250 99,765 sold* Variable selling 23,000 23,000 expenses Total variable expenses 107,250 122,765 Contribution margin 164,750 149,235 Fixed expenses: Manufacturing overhead 64,000 64,000 Selling and 89,000 89,000 administrative Total fixed expenses 153,000 153,000 Net operating income $ 11,750 $ (3,765) (loss) "Contains direct materials, direct labor, and variable manufacturing overhead. Janet Dunn, who has just been appointed general manager of the Westwood Plant, has been given instructions to "get things under control." Upon reviewing the plant's income statement, Ms. Dunn has concluded that the major problem lies in the variable cost of goods sold. She has been provided with the following standard cost per swimming pool: Standard Quantity Standard PriceStandard or Hours or Rate Cost 3.9 pounds $2.50 per pound $ 9.75 Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit 0.8 hours $8.00 per hour 0.2 hours* $3.50 per hour 6.40 0.70 $ 16.85 *Based on machine-hours. During June the plant produced 5,000 pools and incurred the following costs: a. Purchased 24,500 pounds of materials at a cost of $2.95 per pound. b. Used 19,300 pounds of materials in production. (Finished goods and work in process inventories are insignificant and can be ignored.) c. Worked 4,600 direct labor-hours at a cost of $7.70 per hour. d. Incurred variable manufacturing overhead cost totaling $5,070 for the month. A total of 1,300 machine-hours was recorded. It is the company's policy to close all variances to cost of goods sold on a monthly basis. Required: 1. Compute the following variances for June: a. Materials price and quantity variances. b. Labor rate and efficiency variances. c. Variable overhead rate and efficiency variances. 2. Summarize the variances that you computed in (1) above by showing the net overall favorable or unfavorable variance for the month. Complete this question by entering your answers in the tabs belowStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started