Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

1A. Compute the number of calendar days needed to complete a one-acre job using the current truck/trailer combination and the larger truck/trailer combination. Use this

1A. Compute the number of calendar days needed to complete a one-acre job using the current truck/trailer combination and the larger truck/trailer combination. Use this result to calculate the maximum number of jobs McCoy could accept per year using each truck/trailer combination.image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days). Exhibit 1 ACTUAL REVENUES AND COSTS FOR THE RESORT LAND-CLEARING JOB (in U.S. dollars) Per day Project $375.00 $2,625.00 Calendar days needed to complete the project Revenues Revenue per calendar day Total revenues Variable costs Transportation costs Round trip distance (miles) Rate per mile Transportation costs per calendar day Total transportation costs 80 $0.63 $50.40 (352.80) $190.00 Shepherd and dog Rate per calendar day Total shepherd and dog costs Total variable costs per calendar day Contribution margin $240.40 $134.60 (1.330.00) (1,682.80) $942.20 (100.00) Fixed costs Setup Fencing Linear feet Rate per linear foot Total fencing costs Total fixed costs Profit 962 $0.75 (721.50) (821.50) $120.70 The area cleared was one acre, or 43,560 square feet. At a daily forage rate of 250 square feet per goat, the job required 174.24 goat days. The trailer has a capacity of 25 goats, so it would take 6.97 days for the goats to finish clearing the land. By agreement, McCoy billed for a full trailer (25 goats) for a full day each day the goats were on site. Therefore, McCoy billed the owner for seven calendar days (175 goat days)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Karen Wilken Braun, Wendy Tietz, Walter Harrison, Rhonda Pyp

1st Canadian Edition

978-0132490252, 132490250, 978-0176223311

More Books

Students also viewed these Finance questions