Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1.A project manager is building a schedule for proposed projects. How can the project manager see a schedule based on project priority? a. by building

1.A project manager is building a schedule for proposed projects. How can the project manager see a schedule based on project priority?

a. by building links in the Resource Chart between the projects in order of weighted score.

b.by building links in the Team Planner between the projects in order of weighted score

c.by building links in Resource Usage between the projects in order of weighted score.

d.by building links in the Selection Dashboard between the projects in order of weighted score.

2.To evaluate how well projects support goals, which two types of fields should you set up?

a. weighting and performance value

b.goal and weighting

c.weighting and estimated value

d. goal and target result.

3.Why are generic resources considered ideal for portfolio planning?

a. because generic resources identify the individuals working on the tasks

b.because only generic resources can be assigned work tasks

c. because only generic resources can be assigned when setting up the project portfolio.

d. because the specific individuals available to do the work might not be known.

4.A project manager is setting up some generic resources for three proposed projects. What value must the project manager assign in the Maximum Unit cell?

a.1%

b.0%

c.300%

d.100%

5.You have created a schedule for proposed Project Three because that is now an active project. How do you reflect this schedule in the project portfolio?

a. insert the schedule file as a subproject, mark the project Active, link the subject to the successor project, delete Project Three row.

b.insert the schedule file into the project portfolio at the row for Project Three, mark the project Active, then click Update.

c.insert the schedule file into the project portfolio at the row for Project Three, mark the project Active, then click Save.

d.a. insert the schedule file as a subproject, mark the project Active, link the subject to the predecessor project, delete Project Three row.

6.How can a project manager estimate the work demand for the roofing tasks and the painting tasks of five proposed building projects if she doesn't know who will be performing those tasks?

a. he can assign generic resources to the tasks, enter the estimated hours by project duration, keep the units at 0%

b.he can assign generic resources to the tasks, enter the estimated hours by project duration, change the units to 100%

c.he can assign generic resources to the tasks, enter the estimated hours by month, keep the units at 0%

d.he can assign generic resources to the tasks, enter the estimated hours by month, change the units to 100%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions

Question

LO6.1 Discuss price elasticity of demand and how it is calculated.

Answered: 1 week ago