Answered step by step
Verified Expert Solution
Question
1 Approved Answer
1(b) You are managing a second project that has the same time and cost specifications as those in Question 1(a) which is 70% complete at
1(b) You are managing a second project that has the same time and cost specifications as those in Question 1(a) which is 70% complete at the status date, when actual cost is RM700,000 The specifications are as below: Budgeted Actual Cost (BAC) of RM2,000,000 Schedule to complete is 12 months At the Status Date, the project has the following characteristics: Planned value (PV) RM600,000 Actual cost (AC) RM750,000 Percentage of work completed 70% Calculate the following quantities: Earned Value (EV) Cost Variance (CV) Schedule Variance (SV) Cost Performance index (CPI) Schedule performance index (SPI) Using your results, apply the three formulae listed for the calculation of the Estimate Actual Cost at Completion (EAC) of the project 4 marks 3 marks 3 marks 3 marks 3 marks 6 marks For each of these calculations (3 in total), calculate the To-Complete- Performance Index (TCPI). (3 marks) However, if the CPI value is greater than 1, the project is under budgeted. So, the To Complete Performance Index (TCPI) is given as:- TCPI = (BAC-EV)/(BAC-AC) [25 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started