1.Calculate the material variances: standard price per meter $4 actual price per meter $3 standard usage(Quantity) per unit 5 meters actual usage (Quantity) per unit
1.Calculate the material variances:
standard price per meter $4
actual price per meter $3
standard usage(Quantity) per unit 5 meters
actual usage (Quantity) per unit 7 meters
2.Calculate Material Cost Variance from the following information:
standard price of material per kg=$4
standard usage of materials=800kgs
actual usage of materials=920kgs
actual price of materials per kg=$3
3.Calculate labour cost variance from the following information:
standard labour rate=$4
standard hours=800hrs
actual hours=920hrs
actual labour cost=$3
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started