1.Consider a project consisting of multiple activities. You were told that a ceratin activity known as activity M had a normal time of 11 weeks
1.Consider a project consisting of multiple activities. You were told that a ceratin activity known as activity "M" had a normal time of 11 weeks and a crashed time of 9 weeks, but actually took 13 weeks to complete. What is the corresponding expected impact on the project schedule?
A.Unknown- not enough information
B.Project will be delayed by 2 weeks
C.Project will be delay by 4 weeks
D.No impact
2.Which of the following statements about the critical path and critical chain methods of project scheduling is False?
A.the critical chain can be shorter than the critical path
B.the critical chain includes resource constraints
C.the critical path assumes unlimited resources
D.the critical chain can be longer than the critical path
E.None- all of the above statements are true
3.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started