1.Which of the following can be included in scoring models for selecting projects? a)potential profitability of the project b)potential impact on the firm's competitive position
1.Which of the following can be included in scoring models for selecting projects?
a)potential profitability of the project
b)potential impact on the firm's competitive position
c)the organization's ability to market the output of a project
d)All of the above can be included
e)only a and b above
2. If the initial investment in a project is $100,000 and the expected annual net profit for the project is $20,000, the payback period is:
a)5 years
b)4 years
c)One fifth of a year
d)10 years
e)insufficient information to determine the payback period
3.Which of the following is NOT a characteristic of a project?
a)They are unique.
b)They are routine.
c)They have specific due date.
d)They have a specific deliverable.
e)They have a purpose.
4.The project manager is responsible to:
a)the parent organization
b)the project team
c)the project's client
d)the project manager's immediate supervisor
e)all of the above
5. What is the primary purpose of creating a work breakdown structure?
a)to draw the project plan as a chart or tree
b)to make sure important tasks aren't overlooked
c)so that all team members can see what others are working on
d)to assign budget numbers to tasks
e)to identify important precedence relationships
6.Which of the following is used to show linkages between people and tasks?
a)the Work Breakdown Structure
b)the RACI Matrix
c)the Project Action Plan
d)the Project Resource Diagram
e)the Concurrent Engineering Chart
7.Which of the following is NOT a sub-process associated with risk management?
a)risk identification
b)risk measurement
c)qualitative risk analysis
d)quantitative risk analysis
e)risk response planning
8.Which of the following is NOT true regarding top-down budgeting?
a)It is based on the collective judgments of top and middle managers.
b)Overall project costs are estimated by top and middle managers and then passed on to the next lower level.
d)The overall budget cost is generally not very accurate.
e)Overlooking small but important tasks can lead to a serious budgetary problem.
f)All of the above are true concerning top-down budgeting.
9.Which of the following is NOT an element of the Gantt chart?
a)actual progress
b)variance of the critical path
c)the current date
d)scheduled milestones
e)all of the above are elements
10. Which of the following is typically used as the best estimate of task duration?
a)expected time
b)pessimistic time
c)optimistic time
d)most likely time
e)none of the above
11. In MS Project, in order to set a deadline for a particular task, which of the following is the proper sequence from the Task Information dialog box?
a) General > Percent Complete
b) Resources > Assignment Owner
c) Advanced tab > Calendar
d) Advanced tab > Deadline
12. Why is it necessary to consider the learning curve of resources on a project?
a) to estimate labor costs properly
b) to improve project team morale
c) because it always takes less time to do task after someone has done it a few times
d) collective bargaining contracts require it
e) All of the above
13. The name given to the budget process that aggregates income and expenditures across projects is:
a) activity-oriented budget
b) top-down budget
c) bottom-up budget
d) program-oriented budget
e) activity-based costing
14.Which of the following linkages is used to start two or more activities at the same time?
a) finish-to-start
b) start-to-start
c) finish-to-finish
d) start-to-finish
e) They can all be used to start two or more activities at the same time
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started