Question

1 Approved Answer

1.Your state government organization located in the US, has determined that they want to outsource a design project to a consulting engineering firm and they

1.Your state government organization located in the US, has determined that they want to outsource a design project to a consulting engineering firm and they have asked you to be the owner's project manager.One of your tasks is to prepare an RFP to select a firm to do the work.Answer the following questions:

a.List eight criteria below that you will use to decide which firm to select.Following each of the eight, provide a weighting factor that you will assign to each criterion so that the most important criterion has a weighting factor of 8 and the least important has a weighting factor of 1.

b.Should cost be one of your selection criteria?If not, why not and explain what you will do to make sure you are getting the best value?If yes, what form would it take?For example, should the firm submit a competitive total lump sum cost for their work?Or, their labor multiplier?Or, their hourly rates?Or, a man-hour estimate?Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions

Question

1 . Television News channels importantance of our Life pattern ?

Answered: 1 week ago

Question

1. How is the newspaper help to our daily life?

Answered: 1 week ago