( 2 0 points ) 3 . Following completion, a 1 8 - 1 well is produced for some time, believed to be in transient

(20 points)
3. Following completion, a 18-1 well is produced for some time, believed to be in transient behavior, before shut in for a lengthy build up test. The production history is summarised below:
\table[[\table[[Production Time],[(hrs)]],\table[[Total Production],[(rb)]]],[25,68],[14,0],[30,60],[99,88]]
If the fluid and reservoir properties are summarised as follows: k=65md,h=50ft,=0.22,=0.85cp,o=1.35rbstb,Ct=35.0E-06-1, and pi=3500.
I. Calculate the minimum drainage radius.
II. Calculate the wellbore pressure at the end of the seventh day using Horner's approximation if applicable or any other method if it doesn't.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mass And Heat Transfer Analysis Of Mass Contactors And Heat Exchangers

Authors: T. W. Fraser Russell, Anne Skaja Robinson, Norman J. Wagner

1st Edition

0521886708, 9780521886703

More Books

Students also viewed these Chemical Engineering questions