Question

1 Approved Answer

2. A project is estimated to cost $310,862 and provide annual net cash flows of $82,000 for five years. Present Value of an Annuity of

2.

A project is estimated to cost $310,862 and provide annual net cash flows of $82,000 for five years.

Present Value of an Annuity of $1 at Compound Interest
Year 6% 10% 12% 15% 20%
1 0.943 0.909 0.893 0.870 0.833
2 1.833 1.736 1.690 1.626 1.528
3 2.673 2.487 2.402 2.283 2.106
4 3.465 3.170 3.037 2.855 2.589
5 4.212 3.791 3.605 3.353 2.991
6 4.917 4.355 4.111 3.785 3.326
7 5.582 4.868 4.564 4.160 3.605
8 6.210 5.335 4.968 4.487 3.837
9 6.802 5.759 5.328 4.772 4.031
10 7.360 6.145 5.650 5.019 4.192

Determine the internal rate of return for this project, using the Present Value of an Annuity of $1 at Compound Interest table shown above.

_______%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistical Techniques For Analytical Review In Auditing

Authors: Kenneth W. Stringer, Trevor R. Stewart

1st Edition

047186076X, 978-0471860761

More Books

Students also viewed these Accounting questions

Question

Evaluate the integral. (x + 2) 2 (x + 1) 20 dx

Answered: 1 week ago