2 . Activity ExpectedTime Immediate Predecessors Early Finish Late Finish Slack Critical Path? A 4 - - B 6 A C 2 A D 4
Activity
ExpectedTime Immediate Predecessors Early
Finish Late
Finish
Slack Critical
Path?
A
B A
C A
D B
E B
F B C
G D E
H F
I H
J G I