2. Calculate the minimum cost of crashing the following project by four days. pts) Crash Normal Normal Crash Cost Immediate Activity Time Predecessor Time (days)
2. Calculate the minimum cost of crashing the following project by four days. pts) Crash Normal Normal Crash Cost Immediate Activity Time Predecessor Time (days) Cost ($) (S) (days) A 6 5 900 1000 - B 8 6 300 400 - 3 500 600 1 A D u 3 900 1200 8 5 1000 1600 C