Answered step by step
Verified Expert Solution
Question
1 Approved Answer
2 days 4 days 1 day Act. 2 Act. 1 Act. 5 1 day 2 days Act. 3 Act. 4 Which of the following statements
2 days 4 days 1 day Act. 2 Act. 1 Act. 5 1 day 2 days Act. 3 Act. 4 Which of the following statements regarding the above figure is correct? O If activity 2 is crashed by 1 day, the critical activities remain the same. O If activity 3 is crashed by 0.5 day, then the total time to complete the activities is reduced by 0.5 days. O After crashing activity 2 by 2 days, the total time to complete the activities is 6 days. If activity 1 takes 3 days instead of 2 days then the critical path changes
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started