2. E-Motion Visual Enterprise is contracted to finish a filming project predetermined to be completed in 18 months. The filming project's budget is R955 000.

2. E-Motion Visual Enterprise is contracted to finish a filming project predetermined to be completed in 18 months. The filming project's budget is R955 000. Eight (8) months have passed and R725 000 has been spent. Based on the current project progress report, 55% of the work has been completed. Given that the project's Earned Value (EV) is R516 000 and Present Value is R589 000, measure the project performance by calculating the following:

2.1 Schedule variance (SV) and interpret the meaning of the filming project's SV value. (1x4=4 marks)

2.2 Cost variance (CV) and interpret the meaning of the filming project's CV value.

(1x4=4 marks)

2.3 Assuming the filming project is behind schedule, identify and explain two (2) methods at your disposal you can use to compress the project schedule. Substantiate your answer by indicating two (2) ways in which you would apply each method to compress the project schedule. (5x2 =10 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The General Managers

Authors: John P. Kotter

1st Edition

0029182301, 978-0029182307

More Books

Students also viewed these General Management questions

Question

How did the authors avoid the post hoc fallacy?

Answered: 1 week ago

Question

Describe factors that influence training and development.

Answered: 1 week ago

Question

Identify some training issues in the global context.

Answered: 1 week ago