2) Six jobs will be processed in a two-step operation. The first operation involves sanding and the second painting. Processing times are as follows: WORK
2) Six jobs will be processed in a two-step operation. The first operation involves sanding and the second painting. Processing times are as follows:
WORK |SANDING (Hours) |PAINTING (Hours) I 4 5 II 16 14 III 8 7 IV 12 11 V 3 9
a) Determine the sequence that minimizes the total time needed to complete these jobs. (5 points)
b) Determine the total operating time and idle time if any. (5 points)
c) Make the graphic illustration.