Answered step by step
Verified Expert Solution
Question
1 Approved Answer
2. The following table lists the activities of a network along with their time estimates: Activity Predecessor Duration (Days) Optimistic (a) Most Likely (m) Pessimistic
2. The following table lists the activities of a network along with their time estimates: Activity Predecessor Duration (Days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 2 5 8 B None 4 7 16 C A 3 6 9 D A 2 5 8 E C 5 8 11 F D 3 6 15 G B 2 5 14 H E, F 2 5 8 I G 6 9 12 J H, I 0 0 0 (a) Draw the project network. Use activity on node (A-O-N) method. (b) Identify the Critical Path. Calculate the length and variance of the Critical Path. (c) Identify the non-critical activities. Work out the Total Slack (TS) and Free Slack (FS) for all the non-critical activities. (d) State whether the network is sensitive or insensitive! (e) What is the approximate probability that jobs on the critical path will be completed by the due date of (i)24 days, (ii) 29 days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started