Question
2. The work cycle in a worker-machine system consists of (1) external manual work elements with a total normal time of 0.42 min, (2)
2. The work cycle in a worker-machine system consists of (1) external manual work elements with a total normal time of 0.42 min, (2) a machine cycle with machine time of 1.12 min, and (3) internal manual elements with a total normal time of 1.04 min. (a) Determine the standard time for the cycle, using a PFD allowance factor of 15%, and a machine allowance factor of 30%. (b) How many work units are produced daily (8-hour shift) at standard performance? Numbering
Step by Step Solution
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
Solution Gven 1 External momanual work elements with a total normal 7 time of 042 min 2 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Automation Production Systems and Computer Integrated Manufacturing
Authors: Mikell P.Groover
3rd edition
132393212, 978-0132393218
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App