2. XYZ Company has 60 workers distributed equally in 3 shift in the assembly area . Each worker enjoys an hour and 15 minutes.The rate
2. XYZ Company has 60 workers distributed equally in 3 shift in the assembly area . Each worker enjoys an hour and 15 minutes.The rate of output per worker/machine is 25 pcs. The man machine ratio is 1:1 and presently they have 27 machines. They work 5 days in a week and considers 4 weeks in a month.
a.Find the available capacity if a power failure occurred from 8 am to 10:35 am of Day 2 of Week 5.
b. Find the max. capacity for 1 quarter.
c.What is the available capacity for 1 month if power shutdown occurred from 6:00 to 9:35 pm on days 3,4,5 of week 2
d.Find the lost capacity if a material shortage occurred from 6:00 pm to 10:45 pm of Day 4
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started