2- You are in charge of the shearing and pressing operations in a job shop. When you arrived this morning, there were seven jobs with
2- You are in charge of the shearing and pressing operations in a job shop. When you arrived this morning, there were seven jobs with the following processing times. Job Processing Time Shear Press 1 6 3. 2 2 9 3 5 3 4 1 8 5 7 1 6 4 5. 7 9 6 a) What is the makespan under the SPT dispatching rule? b) What sequence yields the minimum makespan? c) What is this makespan