Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

20- In a study, the time (measured or observed time) for a worker to do a job was measured as 5 minutes. The tempo of

20- In a study, the time (measured or observed time) for a worker to do a job was measured as 5 minutes. The tempo of the worker was appreciated as 140% and the shares were estimated to be 5%. Calculate the standard time for the activity. Calculate how many pieces of work the worker will do in a working day. TZ = GZ XD SZ = TZ(1 + a) T SQ SZ

image text in transcribed

20 - In a study, the time (measured or observed time) for a worker to do a job was measured as 5 minutes. The tempo of the worker was appreciated as 140% and the shares were estimated to be 5%. Calculate the standard time for the activity. Calculate how many pieces of work the worker will do in a working day. TZ=GZDSZ=TZ(1+)SQ=SZT

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business and Administrative Communication

Authors: Kitty o. locker, Donna s. kienzler

10th edition

77830105, 978-0077830106, 978-0073403182

More Books

Students also viewed these General Management questions