20 min left In a precedence network, the critical path is the sequence of activities which has: O the most activities O the most nodes.

20 min left

image text in transcribed
In a precedence network, the critical path is the sequence of activities which has: O the most activities O the most nodes. O the most events. O the longest duration O the greatest vanance QUESTION 11 Which of the following isnot a form of risk reduction in project management? O Backup systems O Outsourcing components of the project O Frequent monitoring of project activities O Expand the project scope to reduce external dependencies O Improving communications QUESTION 12 A location analysis has been narrowed down to two locations, A and B. The main factors in the decision will be supply of raw materials, which has a weight of .50, transportation cost, which has a weight of .10, and labour cost, which has a weight of .10. The ratings for raw materials, transportation, and labour are for A-60, 80, and 70, respectively, for B-70, 50, and 90, respectively. Given this information and a minimum acceptable composite score of 75, we can say that the manager should: be indifferent between these locations O choose location A O choose location B O reject both locations

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Launching And Growing Entrepreneurial Ventures

Authors: Justin G. Longenecker, J. William Petty, Leslie E. Palich, Frank Hoy

19th Edition

0357039416, 9780357039410

More Books

Students also viewed these General Management questions