(20) QUESTION 2 The following information is provided for the activities in a building project: Activity Cost Immediate Predecessor(s) Time (weeks) 200 DI B 600
(20) QUESTION 2 The following information is provided for the activities in a building project: Activity Cost Immediate Predecessor(s) Time (weeks) 200 DI B 600 300 CE 7 800 300 F,G 400 2.1 Draw the AON diagram for the project tabulating the forward pass, backward pass and the slack times of each activity (15) What is the completion time for the project? What is the cost of completing the project? 2.2 2.3