Question

1 Approved Answer

2011 2012 2013 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000

2011 2012 2013

Total costs incurred to date $1,500,000 $2,640,000 $4,600,000

Estimated costs to complete 2,500,000 1,760,000 -0-

Customer billings to date 2,200,000 4,000,000 5,600,000

Collections to date 2,000,000 3,500,000 5,500,000

On February 1, 2011, Marsh Contractors agreed to construct a building at a contract price of $6,000,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2013. Information relating to the costs and billings for this contract is as follows:

Percentage-of-Completion Gross Profit Completed-Contract Gross Profit

2011 ___________________________ 2011 ___________________________

2012 ___________________________ 2012 ___________________________

2013 ___________________________ 2013 ___________________________

Instructions: Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2011, 2012, and 2013

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Karen Wilken Braun, Wendy Tietz, Walter Harrison, Rhonda Pyp

1st Canadian Edition

978-0132490252, 132490250, 978-0176223311

More Books

Students also viewed these Accounting questions