In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 2022 2023
Cost incurred during the year: $2,580,000 $4,042,000 $2,175,800
Est. costs- complete for year-end: $6,020,000 1,978,000 $0
Billings during the year: 2,060,000 4,562,000 3,378,000
Cash collections during the year: 1,830,000 4,200,000 3,970,000
Westgate recognizes revenue over time according to percentage of completion.
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
Step by Step Solution
3.45 Rating (145 Votes )
There are 3 Steps involved in it
Step: 1
2021 2022 2023 Percentage of Completion 30 47 100 Revenue 10000000 1...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started