21 If three parallel activities can be connected with both start to start and finish to finish relationships, finish to finish relationships are preferred if:
21 If three parallel activities can be connected with both start to start and finish to finish relationships, finish to finish relationships are preferred if: the three activities have progressively longer durations. the three activities have progressively shorter durations. there are no common shared resources among the three activities. none of the above are true