23 (2 points) (Unit 4) You have been involved in project team which has created a work breakdown structure (WBS). Which of the following best
23 (2 points) (Unit 4) You have been involved in project team which has created a work breakdown structure (WBS). Which of the following best describes the process in which you were involved? Calculating the project schedule Allocating resources to the project work Calculating the total duration of the project Subdividing the deliverables into smaller, more manageable components