23)At the high level of activity in December, 9,000 machine hours were run and power costs were $19,000. In March, a month of low activity,
23)At the high level of activity in December, 9,000 machine hours were run and power costs were $19,000. In March, a month of low activity, 2,500 machine hours were run and power costs amounted to $8,500. Using the high-low method, the estimated fixed cost element of power costs is:
$14,535
$4,037
$4,462
$1.62