25. Why do some projects utilize iterative work? Some of the later work will change based on the outcomes from the earlier work on the
25. Why do some projects utilize iterative work?
Some of the later work will change based on the outcomes from the earlier work on the project
The change request process requires too many approvals
To reduce the amount of time spent in the planning phase
To allow the project team to terminate the project early if the company priorities change
Triple Constraints
26. The curriculum department of a college is working on a project to launch a new major. About 6 months before completing the project, they are notified that due to some tax law changes, an emergency project is needed to update several courses in their accounting programs for the upcoming semester. What triple constraint will be adjusted on the new major project?
A. Scope B. Time C. Cost D. None
27. A project to build a new city library is being planned using federal grant money. The library director, grant administrators, and city planners disagree on some points of the building design. Some stakeholders want to dedicate more community meeting space, while others want more shelves to increase the number of books in the library's collection. Which triple constraint is being debated?
A. Scope B. Time C. Cost D. None
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started