27. Given the following information about a project, calculate the Expected Monetary Value, or EMV: Cost Probability Optimistic $100,000 0.10 Most Likely $130,000 0.80 Pessimistic
27. Given the following information about a project, calculate the Expected Monetary Value, or EMV:
Cost Probability
Optimistic $100,000 0.10
Most Likely $130,000 0.80
Pessimistic $180,000 0.10