28 1 pts A simple CPM network has five activities, A, B, C, D. and E. A is an immediate predecessor of C. D and
28 1 pts A simple CPM network has five activities, A, B, C, D. and E. A is an immediate predecessor of C. D and of E. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Which of the following statements is TRUE? O There are two paths in this network. O There are five paths in this network O There are six paths in this network O There are four paths in this network Previous Next No new data to save. Last checked at 4:08pm Submit Quiz