29. During July actual labor costs amounted to $19,800, the standard rate of pay was $4.50 per hour and the labor rate variance amounted to
29. During July actual labor costs amounted to $19,800, the standard rate of pay was $4.50 per hour and the labor rate variance amounted to $225 adverse. The actual hours worked were:
a. 1,012.5 b. 4,450 c. 4,350 d. 4,400