291 pts In scrum, the burndown chart directly plots: Group of answer choices The cash that has been spent on the project to date. None
291 pts
In scrum, the burndown chart directly plots:
Group of answer choices
The cash that has been spent on the project to date.
None of the other answers is correct.
The number of daily scrums.
The rate at which the project is burning cash.