Question

1 Approved Answer

2.create a significantly offset operating expenses. He recommends savings that grow each year: 5-year project life, 10% discount rate, and a 10% annual savings growth

2.create a significantly offset operating expenses. He recommends savings that grow each year: 5-year project life, 10% discount rate, and a 10% annual savings growth in years 2 through 5. In other words, instead of assuming savings stay flat, assume that they will grow by 10%% in year 2, and then grow another 10% over year 2 in year 3, and so on.Stanley feels that the stated terminal value is reasonable and used it in his calculations.

3. Eva from Engineering believes we use a higher Discount Rate because of the risk of this type of project. As such, she is recommending a 5-year project life and flat annual savings. Eva suggests that even though the equipment is brand new, the updated production process could have a negative impact on other parts of the overall manufacturing costs. She argues that, while it is difficult to quantify the potential negative impacts, to account for the risk, a 12% discount rate should be used. Being an engineer, Eva feels that the stated terminal value is low based on her experience, and is recommending a $75,000 terminal value,

4. Paul, the Product Manager, is convinced the new capability will allow better control of quality and on-time delivery, and that it will last longer than 5 years. He recommends using a 7 Year Equipment Life (which means a 7-year project and that savings will continue for 7 years), flat annual savings, and 10% discount rate. In other words, assume that the machine will last 2 more years and deliver 2 more years of savings. Paul also feels the equipment will have an estimated terminal value of $25,000 at the end of its 7- year useful life as it will be utilized longer thus having less value at the end of the project and savings.

5. Olivia, the head of Operations, is concerned that instead of stabilizing the supply chain, it will just add another process to be managed, and will distract from the core competencies the company currently has. She feels the company should focus on improving communication and supply chain management with its current vendor, and she feels confident he can negotiate a discount of 4% off of the annual outsourcing cost of $1,200,000 if she lets it be known they are considering taking over this step of the process. As there is little risk associated with Olivia's proposal due to no upfront capital requirements, a lower risk-free discount rate of 7% would be appropriate. Oliva feels that any price reductions from the current vendor will last for five years. (NOTE: because there is no "investment", the Payback and IRR metrics are not meaningful.Simply provide the NPV of the Savings cash flows).

Step by Step Solution

3.36 Rating (168 Votes )

There are 3 Steps involved in it

Step: 1

Here are the analyses for each scenario 2 Stanleys analysis 5 year project life 10 di... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Spreadsheet Modeling And Decision Analysis A Practical Introduction To Business Analytics

Authors: Cliff Ragsdale

7th Edition

1285418689, 978-1285969701, 1285969707, 978-1285418681

More Books

Students also viewed these Finance questions

Question

What can you learn from a loan amortization schedule?

Answered: 1 week ago